Saturday, February 7

day . 15

today was our first saturday, and also our first major on site design decision. we decided to move the window that looks out into courtyard down 2 courses of icf. so we had to take it out and cut the icf's so we could lower it. i think it will be really neat when the floor is in. the way the window will now be the sill will be about a foot from the floor were as before it was going to be almost 2 feet off the ground. after that johanna and i went around and counted how many pieces of strapping or bracing that will need to cover the cracks in the icf so the concrete doesn't bust out when it is poured. we ended up needing a lot. after that i moved to help icf the front wall and put in the last window buck. it is really coming along!