so today was more of the same, marking for vertical rebar, and making sure that it was getting cut and bent correctly. robert wanted a final count for how much more rebar we were going to need, so josh and i got that calculated. also we went around and measured over every window where the courses were complete for vertical rebar. once that was cut and bent we were able to get the front wall rebar totally complete.
at the end of the day we had run out of ICFs so we will have to wait for another shipment so who knows when the pour will be. and we have to wait for more rebar too.
at the end of the day we had run out of ICFs so we will have to wait for another shipment so who knows when the pour will be. and we have to wait for more rebar too.