Wednesday, April 8

day . 56

today cody and i got to site at 12:15 to get everything set up so when it was 1 we could get rolling. we were going to start getting the joists up but we had no saw to cut the front ends of them. so as soon as robert got there we busted to get the last 8 up. and we got them done by 2! yay. so we redeemed ourselves from yesterday. after the joist were done we worked on putting blocking inbetween each joist in about 2 feet from the front and 2 feet from the back. this is to keep the joist from racking and keep them upright and parallel. towards the end we found that the 16 inch on center that was supposed to be kept for the joists was not. i was not happy. on the front some of the joist were 15” on center..wth. so therefore we had to make custom blocks for the middle joists. it was a pain.