day . 66


today was more knee walls. we began the day by finishing putting together the last of the knee walls from yesterday. we had to literally drop what we were doing when it started to rain so we had a little to finish. we finally got them all finished and the last 2 installed and plumbed. we then moved on to measuring and cutting the last 2x4’s for the top plates. we got them cut and started to install them around the top of the knee wall. we only got to work on them for a bit before we had to start cleaning the site for our “surprise” tomorrow. which i think is a cookout, but we are not supposed to know! we had to sort through a huge pile of wood that included scrap and pieces that were salvageable. we had to throw out anything that was less than 2 feet long and stack all the good pieces with their like sizes on the other side of the clubhouse. it seemed like the pile kept getting bigger and we were never going to be done. we sorted and moved wood and finally it was done.