more courses we blown off last night! ahh the wind needs to stop, and we have to tie with zip ties better! so today again began with redoing what we did yesterday! doing things twice is not fun! i think this will definitely make us be more careful. once they were fixed more scaffolding arrived and we all unloaded it off the 2 trucks. once it was all unloading gabe and i started assembling it on the front wall. it took all day. and we did not even finish. it is taking way longer to get the scaffolding up than it will take to finish the top 2 courses! we put up about 5 or 6 bays that were 3 stories up! it was smooth sailing until the last 2 bays that did NOT want to cooperate. so that will have to be left until tomorrow. we had a field trip for the lighting class so we all had to get out of there before 6. some of use are coming in early to finish the scaffolding in the morning.